|
The Process

Flipping & Flopping
After achieving its necessary strength, the
Side A panel wythe is ready to be handled as a hardened product.
The computer calls for the steel table which Side A is resting on
to be brought out of the curing room. Once the table fully exits
the curing room, the Side A panels are located beneath an overhead
crane. Workers remove all edge forms and magnets from the perimeter
locations of the panels. At this time, the overhead crane, equipped
with hooked lifting devices, picks up the Side A panel wythe by
its steel trusses. The crane brings the Side A panel wythe over
to the superstructure located above the consolidation station. The
superstructure is commonly referred to as the vacuum flipping device.
The Side A panel wythe is placed (form finished side down) on top
of a series of adjustable vacuum pads that are mounted to the top
of the flipping device. The vacuums are turned on holding the panel(s)
in place in preparation for the procedures to follow.
Concurrently, the Side B panel wythes that will match up to their
partner Side A panel wythes have gone through their paces (layout,
installation of rebar, etc.) and are being filled with concrete.
Immediately after the Side B panel wythe receives its concrete,
the steel table with the Side B panel(s) is sent on rollers to the
shaking and consolidation station (directly beneath the vacuum flipping
device superstructure).
At this time, the vacuum flipping device holding the Side A panel(s)
rotates 180 degrees, thus holding the panel(s) completely upside
down. Then the vacuum flipping device superstructure slowly lowers
the Side A panel wythe until it is joined into the fresh concrete
mixture in the Side B panel wythe via the steel trusses. The procedure
is facilitated with spacers and holdbacks to insure that final sandwich
panel dimensions are the correct, 8, 10, or 12-inch widths. After
the two panel wythes are connected, the shaking and consolidation
procedures begin to thoroughly "marry together" the two
panel wythes and consolidate the finished surface of the Side B
panel wythe.
After this procedure, which effectively forms the double-wall,
is complete, the now joined panels travel to the inspection station
for additional quality control checks; overall panel thickness assured,
insulation barriers installed and edges cleaned. The table now advances
to the curing room for strength gain of the now-composite panel.
|