See Recent Newscasts On Double-Wall Precast Concrete Homes!
Find out more

 

 

 

 

 

 

 

 

 

 

 

 

The Process

Layout

Formliners, Steel Reinforcing, Window Bucks, Electrical Boxes

Concrete Placement

Shaking, Consolidation & Curing

Flippjng & Flopping

Installation of Insulation & Shipping

About Our Plant

 

Side Shot of Foamed Panel Wall    

Installation of Insulation...
After the double-wall panels have achieved their necessary strength (next day typical) they are brought out of the curing room for installation of the insulating foam and readying for shipping to the project site. Exterior wall panels are insulated with 3-1/4 inches of a high R-value (over 7 per inch) insulating foam in the sandwich cavity between the two wythes of concrete. Interior wall panels may or may not be insulated as per the client's needs. In general, floor panels are not insulated, with the exception of the top floor of the building structure.

Wall panels are produced laying flat. However for shipping and erection purposes, the wall panels will be stood upright. The steel table exits the kiln and sets into position over a hydraulic lift which will gradually tilt the entire steel table (containing the wall panels) into an upright position. The overhead crane will pick the wall panel up from its top and place it into its trailer. The two-part insulating foam is then injected into the interior cavity of the panel in a highly controlled manner. After the insulation achieves final set, and the temporary foam-containment forms are removed, the panel is ready for shipping.

When the floor panels are brought out of the kiln, an overhead crane picks up the floor panels and places them directly on the trailer. These floor panels are shipped out flat. If the floor is to be insulated, the insulation operation will proceed at this time. The panels are then inventoried within the plant's storage areas or trucked directly to the project site.