Aurora Public Works
A total of 278 precast pieces were erected, covering 97,500 square feet for the new public works facility. The facility will house office spaces, vehicle maintenance areas, and more to support the City of Aurora's public works operations.
Project Details

Leading the construction is General Contractor R.C. Wegman Construction Company. The architectural and engineering firm Kluber Architects + Engineers designed the new complex.
The erection of columns, beams, walls, and additional precast pieces was performed by the experienced crew from Creative Erectors, LLC.
As the precast manufacturer for the project, we worked closely with the architects during design to provide precast pieces that would meet both aesthetic and functional goals. Our production team then manufactured the pieces with the highest quality standards.