Building Speed, Strength, and Efficiency: Dukane Precast Powers New $60 Million FedEx Distribution Center in Gary, Indiana
- Dukane Precast
- 2 days ago
- 2 min read
The City of Gary recently celebrated the groundbreaking of a new $60 million FedEx Distribution Center, a project that marks a major step in the city’s ongoing industrial and economic revitalization. Dukane Precast is proud to have played a key role in bringing this facility to life by supplying the full precast concrete building system.
As national logistics providers continue to expand rapidly, speed-to-market, durability, and cost efficiency have never been more critical. Precast concrete was the ideal solution for this landmark development—offering the strength, speed, and long-term performance required for a modern distribution environment.
355 Precast Components Installed — 145,400 Square Feet of Structural Performance
Dukane Precast manufactured, delivered, and installed 355 precast components, totaling 145,400 square feet of high-performance wall panels and structural elements.
These components were engineered to provide:
Exceptional durability for a high-traffic logistics environment
Clean architectural lines and consistent finish quality
Long-term resilience against Midwest weather conditions
Thermal efficiency to support operational energy performance
Precast allowed the project team to accelerate construction, maintain quality, and streamline jobsite coordination—key priorities for large-scale industrial facilities.
Fast Delivery: From First Panel to Final Installation in Just 46 Days
One of the most notable successes of this project was the speed of precast erection.
Start Date: October 28
Completion Date: December 12
Within 46 days, the full precast structure was completed—an execution timeline difficult to match with traditional construction methods. This rapid enclosure meant interior work could begin sooner, helping keep the overall project schedule on track during the heart of the Midwest construction season.
This timeline demonstrates why precast continues to be one of the most reliable systems for fast-track industrial development.
Supporting Gary’s Growth and Future Workforce
The new FedEx Distribution Center is expected to strengthen the local economy, expand job opportunities, and attract continued investment into Gary’s industrial corridor. Dukane Precast is honored to contribute to a project that supports community growth and positions the city for long-term success.
As demand for logistics, warehousing, and distribution space increases nationwide, precast concrete continues to serve as a trusted structural solution for developers, contractors, and end users who need speed, durability, and predictable performance.
Dukane Precast: Ready for Your Next Industrial Project
From distribution centers to manufacturing facilities and fulfillment hubs, Dukane Precast delivers the structural systems that help industrial projects move faster and perform better for decades.
If your team is exploring precast for an upcoming development, we’re here to support early planning, design coordination, and budget alignment.
Contact us to discuss your next project.